As you can see from the first picture, Lochside still resembles a beach.
However plenty of work has been completed and the project remains on-schedule. The topsoil has been removed, new underground drainage has been installed and manhole covers placed just outside the fence-line. In addition, electrical conduits have been built to allow for increased amperage to the existing lights as well as for a new light standard at the southeast corner of the park.
However plenty of work has been completed and the project remains on-schedule. The topsoil has been removed, new underground drainage has been installed and manhole covers placed just outside the fence-line. In addition, electrical conduits have been built to allow for increased amperage to the existing lights as well as for a new light standard at the southeast corner of the park.
Concrete forms have been prepared for the north side of the field. Forms for the west side will be completed Thursday and then on Saturday comes 250 tonnes of gravel base.